State IntegrityReceipts, not verdicts

Andrew Jones corrected a written answer on Electric Vehicles: Charging Points

19 June 2015 · Commons written answer · Department for Transport

Barry Gardiner (Labour, Brent North) asked written question 2332 on 12 June 2015. Andrew Jones answered on 17 June 2015 for the Department for Transport, and Andrew Jones corrected the answer on 19 June 2015. The correction replaced 1 figure (21,000) with 6 figures (1,401, 2324, 3,644, 42,423, 579, 9,520). Altogether 207 words differ between the two versions.

The question

To ask the Secretary of State for Transport, how many publicly-funded charging points for electric vehicles have been delivered in each of the last 10 years; and how many such points are planned for delivery in 2015.

Original and corrected answer

Struck through: original only. Bold: correction only.

OriginalCorrected
The Department for Transport ran a public consultation to help inform the specification for the new Northern and TransPennine Express franchises, and received over 21,000 responses; a summary of these have been published on the Government’s website.
The Invitation To Tender
for the Northern franchise has specified the replacement of Pacers (which are currently used) on services between Huddersfield and Sheffield) by the start of 2020, and other rolling stock used on the franchise will be subject to a substantial refurbishment. It also specifies an increase in the Sunday service provision on this route by December 2017. Our process for evaluating franchise bids encourages bidders to exceed the minimum specifications we state, and the bids themselves are due in to the Department by 26 June. We are due to announce the outcome towards the end of the year.
|
|
|
|
|
|
|
|
The number of publicly-funded chargepoints for electric vehicles that have been delivered in each of the last 10 years, including those for domestic use and those that are publicly accessible, is provided below. The first Government funding for chargepoints was in 2010/11 under the Coalition Government. Chargepoint installations in 2015/16 will depend on demand for domestic chargepoints and the detail of new infrastructure schemes to be announced later this year.
2010/11
| 2011/12
| 2012/13
| 2013/14
| 2014/15
579

| 1,401
| 3,644
| 9,520
| 42,423
This question was inadvertently grouped with 2324.

The question and answer on the Parliament website.

More on Andrew Jones.

Receipt

Read fromhttps://questions-statements-api.parliament.uk/api/writtenquestions/questions/353889?expandMember=true
Date read15 October 2026
SHA-256c2688795177b07665022d9b205d48a8ca29a0ecbda222a2cbfea59c488fef149